Short answer

Summarised from paragraphs 4.6 and 4.7 of the Government’s Code of Practice on the Minimum Standards of Living Conditions for BHUs. The toilet and the sink are two of the eight BHU minimum standards.

What must the toilet have?

ItemRequirement
NumberAt least one per SDU, for the exclusive use of its occupants (not shared)
FittingsWater closet, wash basin, and a bathtub or shower
SeparationFloor-to-ceiling partitions and a door separating it from the rest of the unit
LocationNot on a balcony or verandah
DrainageFloor drains, water closet, basin, bathtub and similar fittings must have traps with an effective water seal and anti-siphonage devices
Lighting and ventilationArtificial lighting + mechanical ventilation with at least 5 air changes per hour; air-conditioners do not count (see BHU Windows, Lighting and Ventilation Requirements)

How high must the waterproofing go?

Where waterproofing is carried out under the supervision of a specified professional, the Code of Practice follows Appendix B of Buildings Department practice note APP-105:

LocationWaterproofing extent
Toilet floorThe whole floor
Toilet wallsAt least 0.3 m above finished floor level
Walls around the shower (and 0.3 m beyond)At least 2.2 m above finished floor level; up to the beam soffit if the beam is lower than 2.2 m
Walls near the wash basin1.1 m above floor or 0.3 m above the basin, whichever is higher
Floor under the sinkAt least the floor area covered by the sink
Walls near the sink1.1 m above floor or 0.3 m above the sink, whichever is higher

The work must still be inspected or tested afterwards to confirm there is no leakage.

BHU toilet waterproofing heights: toilet walls at least 0.3 m, around the shower at least 2.2 m, near basin 1.1 m or 0.3 m above, whichever is higher
Waterproofing heights (source: Code of Practice, paras 4.6 and 4.7)

What if the existing toilet is kept?

If the toilet or sink was not completed under a specified professional’s supervision (for example an existing toilet), the specified professional must visually check for signs of leakage during certification and, where needed, carry out a dye test or monitor with an electronic moisture meter; they may also arrange to inspect the flat below or next door. Any leakage must be repaired first.

In practice, if an old toilet already shows signs of leakage, redoing the waterproofing is often quicker than repeated repairs and more likely to pass certification first time.

Can the toilet or sink be on a balcony?

No. The Code of Practice states that the toilet, water supply point and sink must not be on a balcony or verandah. Many older subdivided flats have a toilet or kitchen on the balcony; conversion means moving these facilities indoors, which affects the layout, room sizes and drainage, so plan it at the assessment stage.

Adding a toilet from 1 August 2026: slip-resistant floors

Question 39 of the Government’s FAQ notes that if a flat is converted into SDUs on or after 1 August 2026 and the works require building plan submission or fall under the Minor Works Control System (for example adding a toilet or replacing all drainage pipes within a toilet), bathrooms, kitchens and toilets must have slip-resistant floors. Simply replacing sanitary fittings or re-tiling does not trigger the requirement.

FAQ

Must every BHU have its own toilet? Can toilets be shared?

Every subdivided unit must have at least one enclosed toilet for the exclusive use of its occupants; it cannot be shared with other units.

Can the wash basin in the toilet count as the sink?

No. The Code of Practice requires at least one water supply point and sink outside the toilet.

Is a shower enough, or is a bathtub required?

A shower is enough. The requirement is a bathtub or a shower.

Is a dye test required?

It depends. For toilets not completed under a specified professional’s supervision, the professional carries out a dye test or moisture monitoring where needed; waterproofing done under their supervision must also be inspected or tested afterwards.