Basic Housing Unit Renovation Cost: Why Quotes Come In Higher Than the Government’s HK$50,000+ Estimate
By Holling BHU Certification One-Stop Service | Last updated: 17 November 2026
How much does a Basic Housing Unit (BHU) conversion cost?
In May 2026 the government (Housing Bureau) published two showflats whose conversion cost averages about HK$25,000 to HK$51,000 per subdivided unit. But these are estimates for two basic units whose existing walls already complied. They are not the actual quote for every older unit.
- Two-unit showflat (about 270 sq ft, 2 subdivided units): about $42,100 to $60,100 for the whole flat, roughly $25,000 per unit.
- Three-unit showflat (about 400 sq ft, 3 subdivided units): about $140,200 to $164,200 for the whole flat, roughly $51,000 per unit.
- Neither includes the Specified Professional’s certification fee (from $3,500 per unit).
Actual quotes vary with the walls, toilets, waterproofing and the location of the meters. This article goes through the Housing Bureau’s official presentation item by item to show what the government figures include, what they leave out, and why the quotes you receive may be higher.
Source: Housing Bureau showflat presentation (PDF, in Chinese), May 2026.
1-minute video version: a short Cantonese cartoon covering the three assumptions behind the government estimate and four questions to ask before accepting a quote.

Where does the government’s “just over $50,000” come from?
The Housing Bureau used two real older flats as showflats and estimated what it would cost to convert them into BHUs.
- Showflat A (Nga Tsin Long Road): 2 subdivided units. The existing walls were already non-combustible and smoke-resistant, so no wall work was needed (presentation pp.6 and 9). Estimated at $42,100 to $60,100 for the flat, about $25,000 per unit, with works taking about 3 weeks (pp.10 and 17).
- Showflat B (Kai Tak Road): 3 subdivided units. The walls were generally compliant, but a partition was demolished and rebuilt to enlarge one unit and a new independent toilet was built (pp.21 and 23–26). Estimated at $140,200 to $164,200 for the flat, about $51,000 per unit, with works taking about 4 weeks (pp.27 and 39).
Page 2 of the presentation says the estimates assume simple, safe materials with no luxury fit-out, and keep the original layout where possible. So the “just over $50,000” is the average per unit for showflat B, and it assumes the existing walls already comply.
What does the official estimate include?
These are the items listed on p.17 (showflat A) and p.39 (showflat B), in official estimated amounts (HK$):
| Item | Showflat A | Showflat B |
|---|---|---|
| Replace the flat entrance with a fire door (excl. installation) | $5,000–6,000 | $5,000–6,000 |
| Replace subdivided unit doors with smoke-resistant self-closing doors (excl. installation) | $10,000–12,000 (2 units) | $15,000–18,000 (3 units) |
| Smoke detectors (incl. installation and FS251) | $1,500 | $2,000 |
| Dry powder fire extinguisher (incl. installation and FS251) | $600 | $600 |
| Louvred toilet doors (excl. installation) | $2,000 | $4,000 |
| Separate water meters (incl. application, inspection, installation) | $8,000–14,000 | $12,000–21,000 |
| Separate electricity meters (incl. application, inspection, WR1, installation) | $10,000–14,000 | $15,000–21,000 |
| Demolish and rebuild partition (enlarge one unit) | Not applicable | $10,000 |
| New independent toilet | Not applicable | $40,000 |
| Tap and sink outside the toilet | Not applicable | $12,000 |
| Toilet exhaust fan and duct | Not applicable | $9,600 |
| Installation of the items above that exclude it | $5,000–10,000 | $15,000–20,000 |
| Total for the whole flat | $42,100–60,100 | $140,200–164,200 |
Two things to note: showflat A had no wall work at all, and showflat B’s wall work was only to enlarge a unit. The Housing Bureau does not say what material the new walls used or what their fire rating is.
$61,600
$27,000
$24,000
$15,000
$10,000
$2,600
What does the official estimate not include?
Pages 17 and 39 state several assumptions. A unit that does not meet them will cost more than the official figures:
- Specified Professional’s certification fee: from $3,500 per subdivided unit, not included.
- Water pipes: the meter costs assume the existing pipes are in good condition with no leakage risk, so no re-piping.
- Electrical wiring: the meter costs assume the existing wiring is safe with no leakage risk, so no rewiring.
- Walls: the showflats were chosen because their walls were already non-combustible and smoke-resistant, so no wall upgrade or replacement is listed.
- Finish: only simple, safe materials, with no extra fit-out.
In short, what the official figures do not list is the extra work needed when a unit is in worse condition than the showflats. This is not concealment; the showflats were simply chosen from units in better condition.
Why might the quotes you receive exceed the official estimate?
What follows is our observation from assessing units, not official figures. Comparing the showflat assumptions with the eight BHU standards, the gaps are mainly here:
| Item | Official showflat assumption | Typical older unit in practice |
|---|---|---|
| Partition walls | Existing walls already non-combustible and smoke-resistant, no work needed (pp.6 and 9) | In the units we have assessed, partition walls have almost always needed replacing. Ordinary timber or plasterboard walls look the same from outside; you have to check them against the standard |
| Fire documents for walls | Not listed | The standard requires fire-resistant, smoke-resistant walls but does not spell out what documents must be shown. In our experience certification goes through only if a fire certificate is available, so walls need certified materials |
| Water pipes | Existing pipes assumed good, no re-piping | Supply and drain pipes often need redoing, and the toilet and the sink outside it need a trap and anti-siphon device |
| Electrical wiring | Existing wiring assumed safe, no rewiring | Each unit needs its own meter and distribution board; old wiring and boards often have to be redone |
| Toilet waterproofing | Showflat A had no new toilet; showflat B costed one new toilet at $40,000 | A new or rebuilt toilet needs its wall and floor waterproofing inspected by the Specified Professional, with a water test |
| Drawings and documents | Not listed | Work on partitions or raised floors falls under the Minor Works Control System and needs drawings, documents and signatures |
| Headroom and structural load | Not listed | A solid raised floor can bring headroom below the minimum; new works must be assessed for structural impact |
Fire doors: official estimate versus our quote
The showflats price the flat entrance door and the subdivided unit doors at $5,000 to $6,000 each excluding installation, with installation charged separately (pp.17 and 39). Our quotes are for fire doors supplied and installed, excluding electronic locks. So when comparing with the official figure, check whether installation is included and whether a fire certificate comes with the door; do not compare the door price alone.
Typical items on a BHU quotation
Our quotations are broadly grouped as follows:
- Demolition: removal of all contents, old tiles and old partitions.
- Partition walls: new fire-rated brick or fire-rated gypsum board walls, with fire certificates.
- Fire doors: flat entrance and unit doors.
- Fire safety: separate smoke detectors, corridor fire extinguisher.
- Utilities: concealed power points, separate distribution board, separate electricity and water meters, supply and drain pipes.
- Toilet: three-layer waterproofing and water test, tiling, toilet pan, basin, shower, exhaust fan.
- Other: plastering and painting, false ceiling, cleaning, waste removal, third-party insurance.
Some quotes also include furniture, kitchen cabinets and air conditioners. These are not required for certification, so two quotes can differ simply because they include different things.
The above is Holling’s field observation and quotation categories, not an official rule.

The Specified Professional’s certification fee is extra
The last step of BHU certification is certification by a Specified Professional (a registered architect, registered professional engineer or registered professional surveyor). Pages 17 and 39 of the Housing Bureau presentation state that the showflat estimates exclude this fee, which starts at $3,500 per subdivided unit.
Besides the certification fee, depending on the unit, there may also be:
- Applying for and signing drawings and minor works documents
- Fire service installation certificate FS251
- Electrical completion document WR1
- Documents for applying to the Water Supplies Department for separate water meters
These vary from unit to unit. Fees for certification and signing have no standard rate and are set by each professional; what we have seen is generally higher than the official starting figure of $3,500. So when comparing quotes, first ask whether the certification and document fees are included.
We cover the application process, timeline and fees in a separate article.
Seven questions to ask before accepting a quote
- What material are the partition walls? Is there a fire certificate (for example a fire-rated brick or fire-rated gypsum board system)?
- What is the walls’ fire resistance period? Does it meet the requirement for your unit’s scenario (at least 1 hour of fire resistance plus smoke resistance)?
- Are the entrance and unit doors fire doors? Do they have smoke seals and self-closing function, and a certificate?
- Is the wiring and piping being redone or reused? Are the separate meters and distribution boards included?
- How many layers of toilet waterproofing? Is there a water test, and are the trap and anti-siphon device included?
- Are the Specified Professional’s certification and document fees in the quote? Which documents?
- Does the quote include furniture, air conditioners and appliances? Which are required for certification and which are optional?
Frequently asked questions
The government says a BHU conversion costs only about HK$50,000. Is that true?
The Housing Bureau’s showflat estimates average about $25,000 to $51,000 per subdivided unit (about $25,000 for showflat A and about $51,000 for showflat B). They are estimates for two units whose existing walls already complied. Units in worse condition will cost more.
Why do quotes from different renovation companies vary so much?
There are three common reasons: the existing walls, utilities and toilet differ from unit to unit; a quote may or may not include certification and document fees; and a quote may include non-essential items such as furniture and air conditioners. Compare quotes item by item, not just by total.
Does the official estimate include the Specified Professional’s certification fee?
No. Pages 17 and 39 of the Housing Bureau presentation state that the estimates exclude the certification fee, which starts at $3,500 per subdivided unit.
Do the partition walls always have to be replaced?
It depends on whether the existing walls meet the requirement for your unit’s scenario. The official showflats’ walls already complied, so none were replaced. In the units we have assessed, the partition walls have almost always needed replacing.
How long does a BHU conversion take?
The Housing Bureau estimates about 3 weeks for showflat A and about 4 weeks for showflat B (presentation pp.10 and 27). Actual time depends on the condition of your unit.
What work does a conversion involve? Case studies
To see what a conversion typically includes, these completed cases list each unit’s original problems and the changes made:
- Jordan older building: 4 units rebuilt from bare concrete
- Prince Edward older building: 3 old subdivided units renovated
- Prince Edward tong lau: 3 subdivided units
- Quarry Bay high-rise: bare unit on Hong Kong Island
See all BHU conversion cases →
Next steps
Mind the deadline: existing SDUs must be registered on or before 28 February 2027 to get the grace period. See What SDU Owners Must Do Before 1 March 2027.
To get a sense of what your unit needs, first check it yourself against our article The Eight Minimum Standards for Basic Housing Units. To have us measure and inspect your unit, WhatsApp 6934 8391 with the unit address, floor area and number of subdivided units.
This article is for general reference only. It is not a quotation or professional certification advice. Actual costs depend on the unit’s condition on site, and whether it meets the standards is decided by the Specified Professional’s certification and the Housing Bureau.
Sources and last updated
Last updated: 17 November 2026. Policy may change; please refer to the latest Housing Bureau information.