Prince Edward Older Building: 3 Subdivided Units Converted into Basic Housing Units
By Holling BHU One-stop Certification | Last updated: 19 November 2026
This Holling project is in Prince Edward, Kowloon: a single-block 1960s building with a lift, where three old subdivided units on the same floor were re-planned as Basic Housing Units (BHU) with independent toilets, a sink outside the toilet and a cooking area. The work is complete.
Project summary
- Location: Prince Edward, Kowloon; single-block older building with a lift (completed in the 1960s)
- Units: 3 (same floor)
- Scope: removal of old partitions and finishes, new independent toilets, sinks and cooking areas outside the toilet, flooring and walls, lighting, air-conditioning and power points
- Government minimum standards addressed: No. 5 independent toilet, No. 6 water point and sink outside the toilet, No. 7 lighting and ventilation
- Duration: similar projects usually take 60–90 working days, depending on the scope
- Status: completed
What problems did these units have?
All three were old subdivided units. Unit A was stripped back to bare concrete and the old window, so it had to be re-planned from scratch. In Units B and C, the bed, fridge and cooking items were crammed into one space with no proper cooking area or storage, and the floors and walls were worn. To qualify as a BHU, each unit needs an independent toilet, a water point and sink outside the toilet, and adequate lighting and ventilation.
Similar unit? WhatsApp us for an initial assessment
What was changed in each unit?
Unit A: sleeping, cooking and toilet re-planned from bare concrete



The original window was kept. The kitchen sits by the entrance, with the sink, induction hob, range hood and washing machine on one side. The toilet is fully enclosed, with a glass shower screen and an exhaust fan. The bed is a raised platform with storage, plus a full-height wardrobe.
More photos



Unit B: new layout with a corridor and independent toilet



The bed, fridge, table and chairs used to share one space. Now a corridor leads in, the kitchen and toilet are on the entrance side, and the bedroom is by the window, with drawers under the bed and a sliding wardrobe. The toilet has a window for natural ventilation.
More photos

Unit C: L-shaped kitchen with air-conditioning by the window


Cooking used to happen on a folding table. Now there is an L-shaped kitchen with the sink and washing machine outside the toilet, air-conditioning by the window, and new floors and walls throughout.
More photos



How does the work meet the government’s eight minimum standards?
| Standard | What we did |
|---|---|
| No. 5: Independent toilet | All three units have an enclosed independent toilet with a glass shower screen |
| No. 6: Water point and sink outside the toilet | Each unit has a kitchen sink outside the toilet |
| No. 7: Lighting and ventilation | Openable windows kept; exhaust fans in toilets, and some toilets have windows |
For the other standards (floor area, headroom, fire safety, structure, separate water and electricity meters), see our guide to the eight minimum standards.
FAQ
How long does it take to convert an old subdivided unit into a BHU?
Similar projects usually take 60–90 working days, depending on the number of units and the extent of the work. We can give a more accurate timeline after a site visit.
Can a subdivided unit without its own toilet be converted?
Usually yes, but it depends on drainage, building structure and waterproofing. We inspect the site first and then design the toilet position.
How is the cost calculated?
Cost depends on the number of units and the extent of the work. See our article on BHU conversion costs for why actual quotes can differ from the government estimate.
Related BHU conversion cases
- Prince Edward Tong Lau BHU Case: 3 Units
- Mong Kok BHU Case: 2 Units from Bare Concrete
- Wan Chai BHU Case: 3 Subdivided Units Converted
See all BHU conversion cases →
Want to know if your unit can become a Basic Housing Unit? Send us the district, size and number of partitions, and we will give you an initial assessment.
Note: Photos are real completed-work photos with brightness adjusted. To protect the owner’s privacy, building names and unit addresses are not shown. Holling is a Registered Minor Works Contractor (MWC 227/2023).