Building Department Orders: Can a Subdivided Unit Still Be Registered or Recognised as a BHU?
By Holling One-Stop BHU Certification | Last updated: 23 November 2026
Short answer
- BHU recognition (and renewal): any specified statutory order, notice or direction issued by the Buildings Department or another government department in respect of the subdivided unit (SDU) or the flat it is in must already have been complied with.
- Common examples: removal orders for unauthorised building works (section 24 of the Buildings Ordinance), Mandatory Window Inspection notices, building or drainage repair orders, and fire safety directions.
- Orders that only concern the common parts of the building (for example a Mandatory Building Inspection notice): the specified professional does not need to certify compliance, but the Government will consider whether the common parts pose an imminent danger to life or property.
- Grace-period registration: the published eligibility test only looks at whether the flat had a subsisting SDU tenancy between 4 July and 3 October 2025. Statutory orders are not listed as a condition, but a registration can be cancelled in situations such as imminent danger.
Which orders must be dealt with first?
Appendix 2 of the Government’s Code of Practice on the Minimum Standards of Living Conditions for Basic Housing Units lists the “specified statutory orders, notices or directions” relating to an SDU or its flat. They include:
| Ordinance | Department | Orders, notices or directions (examples) |
|---|---|---|
| Buildings Ordinance (Cap. 123) | Buildings Department | Removal orders under s.24(1) and s.24AA(1), warning notices under s.24C(1), orders to discontinue change of use under s.25, building repair orders under s.26, investigation orders under s.26A, closure orders under s.27, drainage repair orders under s.28, Mandatory Window Inspection notices under s.30C, etc. |
| Fire Safety (Buildings) Ordinance (Cap. 572) | Buildings Department, Fire Services Department | Fire safety directions, fire safety compliance orders, prohibition orders, closure orders |
| Fire Service (Fire Hazard Abatement) Regulation (Cap. 95F) | Fire Services Department | Prohibition orders, closure orders |
| Gas Safety Ordinance, Electricity Ordinance | Electrical and Mechanical Services Department | Improvement notices, notices to rectify electrical installations |
| Waterworks Ordinance (Cap. 102) | Water Supplies Department | Maintenance notices |
The full list and provisions are set out in Appendix 2 of the Code of Practice.
Do orders on the common parts of the building matter?
According to the Government’s briefing materials, the specified professional does not need to certify compliance with orders that relate only to the common parts of the building, such as a Mandatory Building Inspection notice for the whole block. However, when processing a recognition application, the Government will still consider whether the common parts pose an imminent danger or risk to life or property.
In practice, a block-level order generally does not stop an individual SDU from being recognised. If the order concerns your own flat (for example unauthorised works, windows, drainage or electrical installations inside the flat), it must be dealt with first.
How do you find out whether a flat has an order?
Under the Code of Practice, the specified professional should check the Land Register and the Buildings Department and Fire Services Department websites, and ask the owner about the compliance status of any order. Owners can prepare in advance:
- Search the Land Register: removal, repair and drainage orders are usually registered against the property at the Land Registry.
- Check the departments’ websites: some orders and notices can be looked up online.
- Gather your documents: keep any letters, orders or notices you have received, together with proof of compliance (for example a letter confirming the order has been discharged).
If there is an outstanding order, what is the order of work?
- Classify it: does it concern the flat itself or only the common parts, and what works does it need (removal of unauthorised works, repairs, drainage, fire safety or electrical)?
- Plan it with the conversion: works needed to comply with an order are best planned together with the BHU conversion to avoid doing the same work twice. For example, removing unauthorised partitions may change the number of rooms, corridor widths and fire safety requirements.
- Complete the works and obtain confirmation: carry out the works the order requires and get the department’s confirmation.
- Certification and application: the specified professional certifies that the unit meets the eight minimum standards and that the relevant obligations have been discharged, then the application is made on Form BHU-01.
For the rest of the process, see How to Apply for BHU Recognition: 5 Steps, Documents and Timeline.
Not disclosing an order you have received can lead to refusal, and the information may be treated as false or misleading. See Can a BHU Recognition Application Be Refused?
FAQ
Can I still register for the grace period if there is a removal order?
The published eligibility test for grace-period registration is that the flat had at least one subsisting domestic SDU tenancy between 4 July and 3 October 2025; statutory orders are not listed as a condition. However, orders must be complied with before applying for BHU recognition, so they still need to be dealt with during the grace period.
The building has a Mandatory Building Inspection notice. Will it affect my unit’s recognition?
According to the Government, the specified professional does not need to certify compliance with orders that relate only to the common parts, such as a Mandatory Building Inspection notice. The Government will, however, consider whether the common parts pose an imminent danger.
Can unauthorised structures on a rooftop, flat roof or light well be recognised as BHUs?
No. The Government states that unauthorised building works on rooftops, flat roofs, lanes, light wells or yards in breach of the Buildings Ordinance are outside the scope of the BHU regime.
What happens if an order is issued after recognition?
BHU recognition can be cancelled, for example if a rectification notice is not complied with. Renewal applications also require confirmation that relevant orders have been complied with.
Further reading: Do BHU Conversions Need Plan Approval? The Minor Works Control System Explained
Sources
- Basic Housing Units website: Basic Housing Unit Recognition (eligibility)
- Government: Code of Practice on the Minimum Standards of Living Conditions for BHUs, Appendix 2 and para. 4.1.1(c)
- Basic Housing Units website: FAQ (scope, cancellation of registration or recognition)
This article is general information only and is not legal or professional advice. How a particular order is handled is subject to the issuing department’s requirements.