Do BHU Conversions Need Plan Approval? The Minor Works Control System Explained
By Holling One-Stop BHU Certification | Last updated: 24 November 2026
Short answer
- Conversion works are controlled by the Buildings Ordinance: removing old partitions, building new non-load-bearing walls, installing toilets and kitchens, altering or adding drains, thickening floor screeding for pipes, and forming door or ventilation openings are all building works associated with subdivided flats.
- Most do not need plan approval, but must follow the Minor Works Control System (MWCS): minor works that do not involve the building’s structure can be carried out under simplified requirements, without the Buildings Department’s prior approval and consent.
- Subdividing a flat into 3 or more rooms with sanitary fitments, where the number of such rooms exceeds the approved plan, is Class I minor works item 1.41: you must appoint a prescribed building professional (PBP) and a prescribed registered contractor (PRC), and submit MW01 to the Buildings Department at least 7 days before work starts.
- Structural works (for example altering structural members or adding load to a cantilevered slab) are not minor works: an Authorized Person and a Registered Structural Engineer must submit plans, and work can start only after approval and consent.
- Link with BHU recognition: the Government’s Code of Practice says subdivision works should be arranged under the Buildings Ordinance, and plans submitted under the MWCS are not treated as the “reference building plan” for a BHU.
Which conversion works are controlled?
The Buildings Department leaflet What you must know about Subdivision of a Flat lists the common works:
- Removing original non-structural partition walls and erecting new ones
- Installing new toilets and kitchens
- Altering or adding internal drains
- Thickening floor screeding to bury new or diverted drain pipes
- Adding door openings or ventilation openings
To meet the eight BHU minimum standards (such as the separate toilet and sink, fire safety and lighting and ventilation), owners usually need exactly these works, so it pays to work out which category they fall into before starting.
Three categories: exempted, minor works, prior approval

| Category | Examples | What is required |
|---|---|---|
| Exempted works (section 41(3), Buildings Ordinance) | Painting, plastering, replacing non-embedded internal branch pipes, replacing sanitary fitments, removing non-load-bearing partitions with no fire-resistance requirement | No Buildings Department approval and no need to appoint a professional or contractor, but the building regulations still apply |
| Minor works (Class I, II, III) | Building non-load-bearing block walls, laying solid floor screeding, erecting or altering above-ground drains, forming openings in staircase enclosures | Carried out under simplified requirements by a PRC (plus a PBP for Class I), with prescribed forms submitted to the Buildings Department |
| Works needing prior approval | Works involving the building’s structure, or beyond minor works specifications | An Authorized Person and Registered Structural Engineer prepare plans; after approval and consent, a registered contractor carries out the works |
Item 1.41: when is it Class I minor works?
Since 3 October 2012, building non-load-bearing block walls, laying solid floor screeding and erecting or altering above-ground drains for subdivided units have been covered by the MWCS. According to the Buildings Department, Class I item 1.41 applies when:
- a domestic flat is subdivided into 3 or more rooms;
- at least 3 of them have a lavatory, sink, water closet, shower or bathtub; and
- the number of such rooms exceeds the number shown on the original approved plan.
Item 1.41 also has limits: for example, the works must not alter structural members or add load to a cantilevered slab. Because every BHU must have its own separate toilet, converting one flat into 3 or more BHUs will usually fall under this item.
Not item 1.41? Other minor works items may still apply
| Works | Class III | Class I |
|---|---|---|
| Additional non-load-bearing block walls (domestic) | Item 3.39: additional wall length above 0.1 m but not more than 0.3 m per m² of floor area | Item 1.43: beyond the Class III range |
| Thickening floor slabs with solid screeding (domestic) | Item 3.41: thickness limit depends on screed density | Item 1.44: thicker than 25 mm and outside the Class III range |
| Above-ground drains | Separate Class II and III items (2.30, 3.23, 3.24), depending on specification | |
Every item has detailed size and location limits. Which class applies should be decided by a PBP or PRC under the Buildings Department’s Technical Guidelines on Minor Works Control System.
Procedures for each class
| Class | Appoint | Before work | After completion |
|---|---|---|---|
| Class I (e.g. item 1.41) | PBP + PRC | Notice of commencement (MW01) with prescribed plans at least 7 days before | Certificate of completion (MW02) with record plans within 14 days |
| Class II | PRC | Notice of commencement at least 7 days before | Certificate of completion within 14 days |
| Class III | PRC | No advance notice | Certificate of completion (MW05) with plans or a description of the works and photos within 14 days |
The Buildings Department pamphlet notes that a person who arranges minor works and knowingly fails to appoint the required PBP or PRC may be prosecuted, and that a PRC may only carry out the classes, types or items it is registered for.
How do minor works relate to BHU recognition?
- Works must be lawfully arranged: paragraph 4.1.2 of the Government’s Code of Practice says subdivision works should generally follow the current Buildings Ordinance and its subsidiary legislation; minor works carried out under the simplified requirements, designed and supervised by an appointed PBP or PRC, do not need the Buildings Department’s approval and consent.
- Works supervised by the specified professional: the specified professional must make sure the works meet the Buildings Ordinance and its subsidiary legislation (for example, building loading limits) and then certify compliance with the minimum standards after a site inspection.
- MWCS plans are not the reference building plan: paragraph 2.13 of the Code of Practice and question 5 of the Government FAQ say prescribed plans under the MWCS are only for notification and are not formally approved by the Building Authority, so they are not treated as the unit’s reference building plan.
- Slip-resistant floors from 1 August 2026: question 39 of the Government FAQ says that where a flat is converted into SDUs on or after that date and the works need plan submission or are done under the MWCS, bathrooms, kitchens and toilets generally need slip-resistant floors; simply replacing a basin or re-tiling does not trigger this.
- Outstanding Buildings Department orders: the legal liabilities under relevant statutory orders (such as removal orders) must be discharged before applying for recognition. See Buildings Department Orders and BHU Recognition.
What if earlier subdivision works were not done under the MWCS?
For works completed before the site inspection and not supervised by the specified professional, the Code of Practice requires the specified professional to assess and certify that the unit meets the minimum standards and that the relevant legal liabilities have been discharged. BHU recognition and Buildings Department enforcement are separate systems, however: minor works that were neither carried out under the simplified requirements nor approved in advance can still be dealt with by the Buildings Department under the Buildings Ordinance.
In practice, most old subdivided flats need the toilet, drains or partitions redone during conversion. Handling them under the MWCS at the same time lets one set of works cover both the minimum standards and the statutory filings, reducing uncertainty later.
How to check a contractor
The Buildings Department website has a register of Registered Minor Works Contractors (companies). You can search by name or registration number to check the classes and types a contractor is registered for. Holling is a Buildings Department Registered Minor Works Contractor (MWC 227/2023); see our portfolio and services.
If the works touch common parts or shared pipes, check the deed of mutual covenant and the owners’ corporation’s requirements too. See Do BHU Alterations Need Owners’ Corporation Consent?
FAQ
Does converting a subdivided flat into BHUs always need plan approval?
No. Works that do not involve the building’s structure can mostly be carried out under the simplified requirements of the MWCS without prior Buildings Department approval. Works involving the structure or beyond minor works specifications need plans submitted by an Authorized Person and approval and consent before starting.
What is minor works item 1.41?
Building non-load-bearing block walls, laying solid floor screeding and altering above-ground drains to subdivide a domestic flat into 3 or more rooms, at least 3 of which have sanitary fitments and exceed the number on the approved plan, is Class I minor works item 1.41.
Which forms are needed for Class I minor works?
Appoint a PBP and a PRC, submit the notice of commencement (MW01) with prescribed plans at least 7 days before work starts, and submit the certificate of completion (MW02) with record plans within 14 days of completion.
Can plans submitted under the MWCS be used as the BHU reference building plan?
No. MWCS prescribed plans are only for notification and are not formally approved by the Building Authority, so the Government says they are not treated as the reference building plan.
Are replacing sanitary fitments or re-tiling minor works?
Replacing sanitary fitments is generally exempted works, needing no contractor appointment or forms, although the building regulations still apply. Re-tiling also does not trigger the slip-resistant floor requirement from 1 August 2026. Thickening the floor or altering drains at the same time may count as minor works.
Sources
- Buildings Department: What you must know about Subdivision of a Flat
- Buildings Department: Minor Works Related to Subdivided Flats (items 1.41–1.44, 3.39–3.42)
- Buildings Department: Minor Works Control System for interior renovation / alteration and subdivision of a flat (pamphlet)
- Government: Code of Practice on the Minimum Standards of Living Conditions for BHUs, paragraphs 2.13 and 4.1.2
- Basic Housing Units website: FAQ, questions 5 and 39
For general information only. Which category a particular work falls into must be decided by a PBP or PRC based on site conditions and Buildings Department guidance.