Sham Shui Po Tong Lau: 4 Subdivided Units Converted into Basic Housing Units
By Holling BHU One-stop Certification | Last updated: 19 November 2026
This Holling project is in Sham Shui Po District, Kowloon (between Prince Edward and Sham Shui Po): four old subdivided units in a tong lau (an older walk-up tenement building), rebuilt from bare concrete with independent toilets, sinks outside the toilet and kitchens. The work is complete.
Project summary
- Location: Sham Shui Po District, Kowloon (between Prince Edward and Sham Shui Po); tong lau
- Units: 4
- Scope: stripped to bare concrete, new independent toilets with water heaters, kitchen sinks and washing machine spaces outside the toilet, platform beds with storage, flooring, walls and lighting
- Government minimum standards addressed: No. 5 independent toilet, No. 6 water point and sink outside the toilet, No. 7 lighting and ventilation
- Duration: similar projects usually take 60–90 working days, depending on the scope
- Status: completed
What problems did these units have?
The four units in this tong lau were old subdivided units. Some were left as bare concrete after the old finishes were removed; one had a stainless-steel counter and fridge squeezed beside the bed; old toilets used a shower curtain and had exposed pipes. Tong lau buildings are older, so waterproofing, drainage and structural loading need extra attention.
Similar unit? WhatsApp us for an initial assessment
What was changed in each unit?
Unit A: rebuilt from bare concrete, platform bed by the window


Walls were re-plastered and painted, a platform bed with storage was built by the window, and curtains and LED strips were added. The enclosed toilet has a water heater and glass shower screen.
More photos


Unit B: old kitchen turned into kitchen, wardrobe and bed in one line


The old stainless-steel counter was removed and replaced with kitchen cabinets, a sink, cooking area and washing machine space, a full-height wardrobe beside them, and a platform bed with drawers.
More photos


Unit C: bare concrete turned into bedroom with kitchen


The window was kept with a platform bed beside it. The kitchen has an induction hob and range hood, and the sink and washing machine are outside the toilet.
More photos



Unit D: toilet fully renovated, kitchen re-planned

The toilet used a shower curtain and had exposed pipes. Waterproofing and tiles were redone, with a glass shower screen, one-piece WC and wall-hung basin. The kitchen cabinets and washing machine space were rebuilt, and the bed sits by the window.
More photos




How does the work meet the government’s eight minimum standards?
| Standard | What we did |
|---|---|
| No. 5: Independent toilet | All four units have an enclosed independent toilet with a glass shower screen |
| No. 6: Water point and sink outside the toilet | Each unit has a kitchen sink outside the toilet |
| No. 7: Lighting and ventilation | Beds are placed beside openable windows |
For the other standards (floor area, headroom, fire safety, structure, separate water and electricity meters), see our guide to the eight minimum standards.
FAQ
How long does it take to convert a tong lau subdivided unit into a BHU?
Similar projects usually take 60–90 working days, depending on the number of units and the extent of the work. We can give a more accurate timeline after a site visit.
What should I watch for when converting units in an older tong lau?
Standard No. 4 requires compliance with statutory building loading standards, so new partitions, raised floors and water tanks must be checked. Waterproofing and drainage also need re-checking. We assess the site before designing.
How is the cost calculated?
Cost depends on the number of units and the extent of the work. See our article on BHU conversion costs for why actual quotes can differ from the government estimate.
Related BHU conversion cases
- Prince Edward Tong Lau BHU Case: 3 Units
- Prince Edward BHU Case: 3 Subdivided Units Converted
- Mong Kok BHU Case: 2 Units from Bare Concrete
See all BHU conversion cases →
Want to know if your unit can become a Basic Housing Unit? Send us the district, size and number of partitions, and we will give you an initial assessment.
Note: Photos are real completed-work photos with brightness adjusted. To protect the owner’s privacy, building names and unit addresses are not shown. Holling is a Registered Minor Works Contractor (MWC 227/2023).